    太子學舍通訊共構議案進度Prince House telecommunication co-construction Proposal Progress Report

    太子學舍電信通訊共構議案進度

     

    1、改善目的:為長遠持續優化太子學舍水源跟長興兩區之3G、4G通訊訊號品質穩定。

     

    2、預計完成:規劃約在今年底或寒假期間施工(以第3點實際各方作業進度為基準,太子學舍將依法保留通訊共構議案最終設立之決定權)。

     

    3、工程進程:籌畫與規劃→各方呈報內部並初步同意→業者實際勘查建築管線道等作業→施工示意圖討論、修改、建立等→太子建設與五大電信業者相互議約→電信廠商申請NCC特許執照→共構廠商申請台電水源專電→工程與設備最終細勘討論→開始施工(施工期間約1個月)→公告NCC檢測之電磁波安全報告→驗收並公告完成。

     

    4、設置位址:如附檔,水源學舍頂樓、地下室B1、地下室B2長興學舍頂樓、地下室B1、地下室B2。

     

     

    太子學舍服務中心

     

     

     

     Prince House telecommunication co-construction Proposal Progress Report

    1. Objective: to continue to optimize the stability and quality of 3G and 4G signals on Shui Yuan and Chang Hsing campuses.

     

    1. Expected completion: The construction is expected to start around the end of this year or during the winter vacation, (depending on the actual progress of all parties mentioned in No. 3. Prince House will reserve the right to the make the final decision on the telecommunication co-construction proposal according to law).

     

    1. Construction Process: Planning and preparation→All parties submit reports and reach initial agreements→Service providers survey the cable system on-site→Discuss, modify, and establish the construction blueprintsPrince Housing and Development Corp. discusses contracts with the five telecom service providers→Service providers apply for NCC permits and licences → Construction contractors apply for private power service for Shui Yuan from Taiwan Power Company →Final discussion on the details of the construction and equipments → Construction starts (and carries on for one month)→Publish electromagnetic wave safety detection report from NCC → Inspect and announce for completion.

     

    1. Construction sites: as seen in the attachment, the roof, basement floors B1 and B2 in all buildings on Shui Yuan and Chang Hsing campuses.

     

     

    Prince House Service Center